Shaoxing water production project 4 sets of 1200KW units shipped ahead of schedule (Xiao Shunjiang water transfer pumping station)
- Time of issue:2023/04/10
(Summary description)Since September, Ningbo Rongguang unit business department and technical personnel are busy for the Shaoxing City Water Supply Co., Ltd. of water conservancy system to provide power supply protection of the bidding materials to do all kinds of preparations before the bidding.After layers of screening, our company won the bid!
Shaoxing water production project 4 sets of 1200KW units shipped ahead of schedule (Xiao Shunjiang water transfer pumping station)
(Summary description)Since September, Ningbo Rongguang unit business department and technical personnel are busy for the Shaoxing City Water Supply Co., Ltd. of water conservancy system to provide power supply protection of the bidding materials to do all kinds of preparations before the bidding.After layers of screening, our company won the bid!
- Categories:Company news
- Author:
- Origin:
- Time of issue:2023-04-10 21:11
- Views:
Since September, Ningbo Rongguang unit business department and technical personnel are busy for the Shaoxing City Water Supply Co., Ltd. of water conservancy system to provide power supply protection of the bidding materials to do all kinds of preparations before the bidding.After layers of screening, our company won the bid!
After two and a half months, all the participants in this project, such as business, design, procurement, installation, outsourcing, cold work, assembly, commissioning and other personnel to overcome all the difficulties, and finally on December 25, 2019 ahead of schedule shipment. The silent compartment unit is simple and generous in appearance, and the internal unit has many advantages such as reasonable hardware layout, excellent configuration, compact structure, small footprint, and convenient management and maintenance.
This project is the year-end project of our company and the time is tight, the task is heavy, and all of them are assembled by silent compartment type production. All the staff of the production department in the relevant departments of the full cooperation, ahead of schedule to complete the integration task. For the company to complete the task in time and quality to play a beautiful card for the company's benefit to save time, won the time. It can be said that the company's integration of power plant work on another milestone model project.